Solar information
Interconnection
The Maine Public Utilities Commission has issued rules and procedures for Small Generator Interconnections under Chapter 324. These rules and procedures establish statewide standards for the interconnection of small renewable energy facilities to the energy grid. The purpose of these rules and procedures is to increase the efficiency of the interconnection process, encourage the increased use of renewable energy and distributed generation. We have provided links to the forms and agreements that need to be completed in order to begin the process.
Chapter 324
- Please use the following link to obtain a copy of Chapter 324: https://www.maine.gov/mpuc/legislative/rules/part3-electric.shtml
- For commercial customers submitting applications, please provide your tax id number
- As required by order of the Maine Public Utilities Commission, Small Generator Interconnection Applications will be evaluated under applicable screening criteria based on the overall AC generation capacity of the customer-generation facility at the point of interconnection.
- Please use the following link to access the most recent list of Central Maine Power’s Distribution Interconnection projects:
MEW MPUC Chapter 324 interconnection Project List
Pay Your Bill Online